23 Jul 2025, 12:39
S枚ren Amelang
|
Germany

Germany doesn鈥檛 connect a single offshore wind turbine to grid in first half of 2025

麻豆无码版

The number of Germany鈥檚 offshore wind turbines connected to the grid has remained stuck at 1,639 since the end of 2024,聽the country鈥檚 offshore wind association BWO .聽Their combined capacity adds up to 9.2 gigawatts (GW).聽聽At the end of June 2025, turbines with a further capacity of 1.9 GW were under construction, while 3.6 GW had received a final investment decision, and 17.5 GW had been allocated, BWO said.

鈥淭he Borkum Riffgrund 3 wind farm, with an expected capacity of 959聽[megawatt]聽MW, is completed, but due to delays in the construction of the grid connection system, it will not be able to feed electricity into the grid until 2026,鈥 BWO said.

The industry group called for changing the tender design to lower costs and smoothen the roll-out, which has slowed in the past years. 鈥淯p to 30 percent cost reduction potential is possible through a reform of the tendering design,鈥澛爐he association argued.

The lobby group said the framework conditions have changed significantly since current rules were introduced in 2021. 鈥淭his year's auctions prove that investor interest is waning and bid totals have slumped by over 90 percent compared to previous years.鈥 BWO blamed rigid implementation deadlines and a lack of safeguard mechanisms for the decrease.

Germany has made offshore wind power a key pillar of its plans for an almost fully renewable electricity supply. Industry said at the start of the year that Germany is likely to reach its target of having a total offshore wind electricity capacity of 30 gigawatt (GW) in 2031, one year later than planned.

Support our work

If you enjoyed reading this article, please consider donating to 麻豆无码版. Our journalism is free to all, and you can help to keep it that way.

All texts created by the 麻豆无码版 are available under a . They can be copied, shared and made publicly accessible by users so long as they give appropriate credit, provide a link to the license, and indicate if changes were made.
« previous news next news »

Ask 麻豆无码版

Researching a story? Drop 麻豆无码版 a line or give us a call for background material and contacts.

Get support

+49 30 62858 497

Journalism for the energy transition

Get our Newsletter
Join our Network
Find an interviewee